Seplat Set to Double Gas Supply to NLNG by Early 2027
Seplat Energy is moving forward with a pipeline upgrade that will double its gas supply capacity to Nigeria LNG (NLNG) from 120 million standard cubic feet per day (MMscfd) to 240 MMscfd.

Seplat Energy is moving forward with a pipeline upgrade that will double its gas supply capacity to Nigeria LNG (NLNG) from 120 million standard cubic feet per day (MMscfd) to 240 MMscfd.
The company says its third-quarter 2026 operations report that the project is still on track to finish in the fourth quarter of 2026.
It said key engineering and construction work on the Oso–Bonny River Terminal (BRT) Phase 1 project moved ahead during the quarter. This included mobilising for the BRT scope and preparing for final execution. Seplat expects the upgraded line to start contributing to production in early 2027, after a section of the Oso–BRT pipeline has been replaced.
The upgrade comes after earlier damage to the pipeline. Seplat recorded no gas sales from Oso in the quarter. It kept gas production only high enough to power the Bonny River Terminal.
Repairs to the damaged line are taking place alongside the upgrade. While the damaged 12-inch gas pipeline section is replaced, Seplat has hired a compressed natural gas power provider to keep the terminal running. The company said this temporary fix keeps natural gas liquids production going and limits the impact of the outage.
ANOH plant ramps up
Seplat’s ANOH Gas Processing Company (AGPC) kept growing. Its gross output averaged 164 MMscfd in the third quarter, and the plant is now running at 70–80% of nameplate capacity. AGPC also passed a test at full nameplate throughput during the quarter, which the company said supports further growth.
Most of the processed gas went to NLNG and Indorama. NNPC Gas Infrastructure Company Limited finished and commissioned the OB3 pipeline during the quarter, and commercial gas flow from ANOH through OB3 began on 1 September. About 10% of third-quarter gas sales went through the new pipeline.
AGPC also started exporting condensate. Exports through the Trans Niger Pipeline (TNP) to Bonny Terminal began on 14 July, and the company completed its first condensate lifting of 641,000 barrels. A second lifting of 551,000 barrels followed at the end of August. A third, of 1.19 million barrels, is planned for early in the fourth quarter. Smaller volumes are still loaded straight from the plant for the domestic market.
ANOH has 12,500 barrels of oil per day of reserved production capacity in the TNP, plus about 1,000 barrels per day of contracted offtake off-the-fence.
AGPC also made its first principal repayments on its debt during the quarter, paying lenders a total of $68 million.